Meeting called to order at 6:40 p.m.

Minutes approved.

P 1 - 2102 Darrow Avenue plat of resubdivision

Rue Simmons says she supports the proposal, says would meet zoning requirements and will add additional housing to the neighborhood.

Approved

P 2 - Special use for type 2 restaurant, Spice, at 1905 Church St.

Approved with suspension of the rules for final action tonight.

P 3 - Special use for type 2 restaurant, Philz Coffee, at 1030 Davis St.

Approved with suspension of the rules for final action tonight.

P 4 - Zoning relief for 2626 Reese Ave.

Alderman Tom Suffredin, 6th Ward, says have new proposal received this morning. Says it's too short notice to consider this tonight. Moves to hold to a future meeting TBD.

Neighbor on south side of property says it's been going on for three years.

Claims developer's plans are misleading and fraudulent

Another neighbor complains that the developer turned down his offer to buy the lot for $25,000.

Vote is to table to a future date TBD.

P 5 - Planned Devleopment at 1714-1720 Chicago Ave.

Fiske moves introduction Rue Simmons seconds.

Architect Paul Janicki presents revised plans for the project.

Says have reduced four level parking garage to three levels and reduced nine stories of office space to eight stories. (These now match the original proposal.)

Three levels of parking provides 74 spaces of public parking -- that's what now proposlng



The previous proposal on the left and the new proposal on the right.

Alderman Melissa Wynne, 3rd Ward, says need more detail.

Janicki says would plan to lease 50 spaces in the Church Street garage.

Alderman Judy Fiske, 1st Ward, says looked at various options for parking. Says suggestion was that all 74 spaces in the surface lot would be replaced and tenant parking would be in the Church Street garage. Says city has done that before with other developments. Says there is plenty of parking available in the garage.

Says she appreciates trying to work this out -- balancing a number of different things on the project -- and thinks its a good conclusions.

Traffic engineer says don't have to back from Church Street to get to the loading dock.

Wynne asks how soon expect to be fully leased. Greg Stec, developer says expects to be fully occupied within 18 months of completion. Says could have 300 to 500 employees -- depending on who the tenant companies are.

Corporation Counsel Michelle Masoncup says city ordinance would likely require a long-term lease for the off-site parking.

Alderman Don Wilson, 4th Ward, says the alley has been used as a cut through for library patrons and others. Those concerns are real.

Janicki says the new building will control pedestrian traffic onto the crosswalk.

Wilson says realistically cars won't stop for stop signs. Have to be mindful of the site lines to be sure the driver will stop.

Alderman Ann Rainey, 8th Ward, says alley is there is a problem whether its an office building or a restaurant. Says people will have to adjust if a building is built.

Wants to hear from staff whether changes make the building more acceptable to staff.

Johanna Leonard, community development director, says staff didn't have any interaction with the developer since the last P & D meeting.

Fiske says when she asked to have the proposal held over at the last meeting she wanted to see the parking and height issues addressed.

Fiske says the building will make for a much safer route for pedestrians to take.

Says has proposal to relocate handicap pedestrian access for 1738 Chicago Ave. from the alley to Chicago Avenue.

Wynne says 213 parking spaces required for the office building (under basic code requirements).

Stec says it's a transit oriented development -- a lot of workers will likely be using mass transit.

Parking Manager Jill Velan says from 7p to 7a there are average 15 percent occupany in early moring fills up gets to 20 to 25 percent

peake times between 11a and 3p  reach 50 percent occupancy ... about 3 days a month get to 70 percent occupancy. For entire year get to 90 percent occupancy perhaps two days a year -- including on the 4th of July.

There are 589 spaces for the public in the garage. Generally over 200 plus spaces are available.

Says wants the option of switching parking to the other garages -- to give the city more flexibility to use any of the garages to use the demand.

Evanston Place, has about 300 spaces they own in the garage and those, Velan says, are only about 30 percent leased -- so there may be options for obtaining extra parking there.

Fiske says deveoper has spent almost a $250,000 on the plans so far. Her suggestion was to bring the revised proposal to the committee and getting some feedback before redoing the entire application as amended at Council in two weeks rather than holding it in committee.

Public Comment

Lorie Halick, 1738 Chicago Ave., asks about property taxes and what current revenue is from parking lot.

Joan Safford, 1618 Wesley Ave., objects to zoning change.

Other opponents of the development say it should be sent back to the start of the project review process.

End of public comment

Fiske .. says zoning on Orrington face of the block is D3 and D2, so rezoning the parking lot wouldn't be spot zoning.

Says since the exising R6 zoning would allow an even taller building that's being proposed now. Says office building would be a quiet, cleaner use for all of its neighbors -- especially compared to a downtown residential building with a lot of move-ins and move-outs. Office building also likely to be quieter at night than a residential development.

Says this developer has been patient and easy to work with, to sit down with everyone and try to solve problems with the understanding that this is a unique lot. Says often don't see that from developers.

Says understand some people would like to start the process over again. Says that's not the proper process and hasn't been how other development have been handled. Says this is somethig for the Council to consider.

Alderman Eleanor Revelle, 7th Ward, says appreciates that developer has come back with more of what have asked for. Says doesn't think aldermen appreciated how difficult it would be to design an office building for this site. Appreciates that its now closer to what the purchase and sale agreement asked for. But she's still worried about the minimal side yard setbacks. Says will doom historic trees on WCTU property and cast a deep shadow on the campus.

Also concerned about alley issues. Doesn't think public benefits are sufficient.

Says $4 million to the city for the sale would be nice, but not enough to justify the compromises required.

Wilson says DAPR and Plan Commission did good job of laying out the issues. Says don't think would change the outcome to send it back. Shouldn't keep putting the developers through more hoops. Wants to have complete materials well before the next meeting, if are going to vote then.

Wynne agrees with Revelle. Says regrets her vote in favor of an RFP for this site without understanding fully what could have been built. Something else may come to the city later. Don't think should sell it for residential use, though.

Motion to introduce carries 5-2. Wynne and Revelle vote no.

Meeting adjourned at 8:10 pm.