A community meeting to answer questions about the construction of the new Robert Crown Community Center, Ice Complex, and Library Branch has been scheduled for 7:30 a.m. on Friday, Nov. 30, at the construction trailer on site at 1801 Main St.
The meeting enables community members to ask questions of the construction manager on progress so far, as well as a forecast of upcoming work, construction traffic, and any other questions.
In the meantime, the construction manager reported, in the most recent holiday-shortened week, that work has continued on installation of the foundation system, site utility, and relocation of the tennis court lights.
In the week ahead, workers will continue foundation system installation, site utility work, and underground utility work.