robert_crown_30nov18

Installation of the underground drainage system is to begin next week as part of the ongoing construction work at the new Robert Crown construction project at Main Street and Dodge Avenue.

In the weekly report Friday from the project manager, installation of the foundation system occupied much of last week and will continue in the week ahead, as will underground mechanical/electrical/plumbing work.

None of the work, including activity on Saturday, will affect existing traffic patterns around the project, according to the weekly update.

A resident of Evanston since 1975, Chuck Bartling holds a master’s degree in journalism from Northwestern University and has extensive experience as a reporter and editor for daily newspapers, radio...

Leave a comment

The goal of our comment policy is to make the comments section a vibrant yet civil space. Treat each other with respect — even the people you disagree with. Whenever possible, provide links to credible documentary evidence to back up your factual claims.

Your email address will not be published. Required fields are marked *